Korea Saemangeum New Port Embankment Phase 1 Construction/DCM Construction
Summary
It is a construction to create two berths for miscellaneous docks that can be docked by up to 50,000 tons of ships to handle port traffic occurring in Saemangeum Industrial Complex, as well as a connection lake and related sites to prevent damage caused by algae and waves. The maximum DCM diameter and maximum DCM construction cross-sectional area in Korea have been applied (7.281m2).
-
Begin 2022.12
Client Ministry of Oceans and Fisheries
-
Location Gunsan, Jeollabuk-do, Republic of Korea
Explanation Off-Shore DCM Improvement: 743,492㎥ (D1600mm*4drivers)